Legacy Of Hope Total Giving

$38,525.88

(Updated: December 28, 2020)

Cost Breakdown

Below is a breakdown of what has been spent thus far.

City / Building Fees

City Permit, Inspection, Volunteer Insurance

$25,441.10

City/building Permits

Contractor Fees

$11,114.97

Architect

Materials

$18,817.88

Paint, flooring, construction supplies/rentals, demolition, etc

Total Expense Thus Far

This is the total amount spent to date.

$55,373.95

What we have left

Below are the areas still needed to complete our church building. Items/Areas are listed in order of priority starting with Tier 1 as a top priority and ending with Tier 3. Areas marked with an asterisk represents price quotes we are still waiting on, however, once those amounts are identified, they will be updated on this page.

TIER 1

Contractor Fee

$10,000 - $15,000

Electrician Contractor

*

Fire Sprinkler Installer

*

HVAC

*

Plumbing Material

TIER 2

Hardware

$4,800

Storefront entrance / exit

*

Restroom fixtures and partitians, water fountain

*

Interior door & doorways

Paint

$3,500

Interior walls

TIER 3

Signage

$5,000

Exterior & Interior signage

Furnishings

$10,000

Furniture / equiptment for lobby, nursery, cry room and kid’s area

AVL

Audio, Visual & Lighting

$10,000

Stage, Berhinger s32, Behringer P16 & P16D, Lighting console, Mac Mini, Lighting, etc